This paper was first presented by Louis Medcalf, FCSI, CCS, SCIP and David Stutzman, AIA, CSI, CCS, SCIP at the National Institute of Building Sciences BEST 5 triennial national conference in Philadelphia, PA April 16, 2018.
Despite innovations in software technology for producing accurate drawing and specification documentation, the quality of contract documents for construction has been steadily declining. The authors as specification consultants for a large number of firms have a unique perspective because they view drawings from multiple sources across the country and have to deal with getting timely decisions on products and basic contracting requirements to provide specifications. We are deeply concerned that there is a coming crisis in construction document quality and are in the process of investing time and resources to develop tools that we believe could help project teams avoid this crisis.
Poor documentation has negative effects on all participants in a project:
Owners may be subject to excessive change orders, which in turn may affect their relationship with lenders, delay project completion, and disrupt planned revenue. Poor documentation may result in dissatisfaction by the people who occupy and use the completed facility, which in extreme cases can lead to legal claims. Most Owners do not have in-house technical staff to perform quality control oversight over the production process or the final set of construction documents. One of the authors of this paper has performed three peer reviews of documents for large, complex projects prepared by other firms to provide an independent, objective quality analysis for the Owner’s benefit.
Although the Construction team can recover most costs for change orders, the cost of preparing such requests and preparing excessive numbers of Requests For Information (RFIs) and for extensive meetings to resolve ambiguities and mistakes in documentation come out of its basic fee, to say nothing of the effects of scheduling changes and frustration on staff.
Design teams have costs for working on change orders and answering RFIs and other field questions that come out of its basic fee and have negative effects on its staff with regard to frustration, interruption of other productive work, and overtime. Negative effects experienced by the Owner may result in not being considered for future work or even loss of reputation, thus resulting in loss of potential future income.
All projects inevitably have some changes and unforeseen circumstances that must be resolved during the construction period. Construction and Design teams include an estimated level of costs in their fees, but because most fees are stipulated sums the ability to recover costs that exceed those estimates is very limited. When excessive costs are the result of inadequate contract documents, the Construction team is in a much better position to recover costs than the Design team. Ultimately it is the owner that bears the risk of increased costs, delayed completion, and financial disruption.
Drawings today are almost universally produced on computers with two-dimensional CAD or three-dimensional BIM software, which make it all too easy to copy mistakes. At present, the output for contracting purposes are two-dimensional drawings, whether distributed as printed sheets or in electronic form. At some point Building Information Modeling (BIM) files may be used for permitting and contracting. Whatever the form of output, drawing errors and resulting re-drawing effort have multiple avoidable causes:
Specifications and Contract Administration are two subjects that are generally not taught in a meaningful way in architectural and engineering colleges. In our experience, few people charged with these tasks supplement their formal education with reading books on the subject or taking supplementary courses since it is possible to pass registration exams without doing so. Although AIA general conditions state that drawings and specifications are at the same level of precedence, most lawyers and other people outside the A/E/C industry believe that specifications should take precedence over drawings and in event of a claim. Owner general conditions written by their lawyers state that specifications take precedence over drawings. Despite these facts, few architects and engineers expend the same level of effort in producing specifications as drawings.
Likewise, few firms of any size have an effective QA/QC program that is consistently followed. Many do not even have guidelines for time to be expended in QC reviews. A survey of QC reviewing at a large multi-office, multi-discipline firm by one of the authors discovered that most reviewers had less than one day to review drawing sets and less than half the time had access to specifications to verify coordination.
At the same time that design fees are declining, building design projects have been steadily increasing in complexity, there are increasing demands from Owners and Construction team to shorten both production time and response to contract administration tasks such as submittals, RFIs, change orders, and other decision documentation. This increase in complexity is a result of more complex regulatory requirements, technological developments, the increasing number of available construction products, and the visualization capabilities provided by BIM. It is the basic thesis of this paper that only those firms that develop and consistently implement a quality assurance and quality control program will be able to succeed in this environment. Many firms have partial approaches to quality and may be implementing ‘lean’ design procedures, but do not have a comprehensive strategic plan that is consistently used. Such QA/QC programs must be developed for the individual firm’s size, staff, and areas of practice. This paper has broad stroke recommendations for developing a comprehensive quality management program to help design firms achieve their aspirations, satisfaction, and profitability, and to avoid costly claims.
Traditionally, Owner project requirements, summary of regulatory requirements relevant to the specific project, and the responses of the project team to those constraints have been in separate documents, which are often not available to all members of the design team that are making design decisions and product selections. Although it is common for privately-funded projects to select a general contractor at the same time or even before selecting an architect, there is often little input from the construction team at conceptual and schematic phases. Pricing and value adjustment is usually reactive and performed after the design team has prepared preliminary drawings and specifications, which then requires much re-work on the part of the Design Team and can result in significant schedule delays for the Owner.
As observed above, registration exams for architects, interior designers, and engineers do not verify proficiency for certain basic responsibilities necessary for protection of the public. Because colleges do not provide meaningful courses to prepare potential registrants for such tasks, it follows that design firms should have an organized educational program to make up for deficiencies in formal education. Learning how to make wise, informed decisions for planning production, product selection, and detailing are things that graduates are expected to learn through mentoring. The question is then whether design firms have effective programs for instructing staff in critical tasks that were not part of their college education. To be effective, a level of structure for such an educational process must be part of a Quality Management program.
It is ironic that architects and engineers require transparency from the Construction Team in the form of detailed construction schedules on behalf of the Owner, but seldom provide such information themselves for the design process. Planning project decisions, whether by the Owner, Design Team, or Construction team, should be part of production planning. In our experience, other than listing dates for various meetings and deliverables Design Teams seldom plan their work in detail. As a result, major decisions are often deferred to the Construction Documents phase, resulting in disruptions and re-work needed to change decisions to meet budgetary constraints or to coordinate with other elements. Such changes at late stages in the project have a profound ripple effect that affects multiple disciplines, impacts the schedule and complicated document coordination.
Interdisciplinary coordination and verification reviews are an essential subset of an effective overall QA/QC program, but is neglected when documents are reviewed in single discipline “silos.” Crucial to the success of quality management is overlay comparison of drawings and use of checklists to check documents. William Nigro invented his RediCheck™ interdisciplinary coordination review process while a civilian employee of the Navy. Although primarily concerned with drawings, implementation of his methodology greatly reduced the number and severity of requests for change orders. Today the RediCheck™ firm has multiple offices that offer this specific service to Design Teams and Owners. As valuable as effective interdisciplinary reviews are, planning positive coordination activities is even more important and can save valuable time. Successful coordination depends on clear communication of project design decisions so that all members of the Design Team have access to such information to base their own discipline decisions.
Many firms limit their Quality Management to producing drawing standards that, all too often, relate primarily to formatting rather than content. It is common that there is not a plan for periodic reviews of standard details, with the result that elements are depicted that do not meet current regulatory requirements or are impractical to build. Even when firms have a written QA/QC program, schedule pressures or lack of training in its implementation hinder implementation.
A conceptual outline for a successful QA/QC program has four processes whose relationships are shown in the following conceptual diagram:
Figure 1 Matrix diagram of the relationship of essential processes for developing an effective QA/QC program.
Bullet items in the following quadrant descriptions are not exhaustive, but are offered as a starting point for discussions to plan and document a comprehensive, coordinated QA/QC program.
The first quadrant covers identification of standards and training needed by the firm for stabling consistent content of construction documents. Firms need to document their corporate memory and what they aspire to be. All activities in this process should have regular reviews to identify things that need updating. A basic purpose of this quadrant is to establish a set of expectations needed to achieve appropriate levels of productivity and quality.
Abraham Lincoln once said, “If you give me three hours to cut down a tree, I’ll spend two hours sharpening my axe.” Army training for officers includes the principle that the less time you have to accomplish a mission, the more time you need to spend planning. It is essential that a critical path of design decisions be developed and followed during production to avoid postponing difficult decisions, especially when projects are fast-tracked with more than one work package, as is increasingly the case.
As indicated in Figure 1, this activity is performed by the project team itself and should always utilize checklists. Checklists should be developed as a Quadrant 1 activity. To ensure that the checklists are both short enough for practical use and detailed enough to be effective. All of us have seen detailed, ‘micro-management’ checklists that are too onerous to use. Checklists should following the Pareto Rule that 20% of issues cause 80% of the problems. Feedback from QC reviewers and contract administration staff should inform what items need to be included.
Off-team reviews by qualified staff who can provide an objective look at the documents is an essential part of Quality Management. Charles Nelson in Managing Quality in Architecture states, “'The person most likely to miss an error or omission is the person who made the error or "created" the omission. Conversely, the less a person knows about a project, the more likely it is that [a reviewer] will question things that don't seem quite right or quite complete.”
A QA/QC program should have provisions for learning from experience. Some firms issue “Lessons Learned” technical bulletins and have a library of them. All the factors that go into the present level of complexity of building design projects will continue to increase, and design firms must learn how to turn experience into improvements both for quality and productivity.
Fred Stitt of the San Francisco Institute of Architect, who has written several books on productivity, has found in his research that over half the time expended on an average architectural drawing sheet is used for redrawing. Although not explored in detail in this paper, design firms need to eliminate both redrawing and unessential things from drawings and specifications. In our experience most sets of drawings have notes, dimensions, and even whole details or sections that are not needed by the Construction Team to build the project, while at the same time essential information is missing. A basic tenet of the ‘lean design’ movement is eliminating waste by tracking the value stream. Why have notes to identify products inside a reference bubble that duplicate notes in the referenced large-scale detail?
As stated above, a major factor in collaborative decision management is the fact that Owner requirements and other planning documents are generally multiple documents rather than a progressive stream of information located in a single location that is available to the Owner, Design Team, Construction Team, and other stakeholders. One of the authors while leading a peer review of construction documents for a new major hospital used the 30+ page Owner Project Requirements document to create a review checklist to verify that the Owner’s expectations would be met. The review team found that only about 2/3 of the requirements were implemented in the design, which likely was a result of the fact that it was a separate document rather than being integrated into the design planning process.
Conspectus, Inc. promotes rethinking specifications as a quality assurance and quality control tool to serve a project from inception through operations. Specifications are more than the MasterFormat based construction specifications. Instead, they are all the non-graphical project requirements, including owner project requirements, regulatory requirements, design criteria, and the designed solutions. Specifications are essential data that are used to measure the Design Team's response to the problem the owner wishes to solve.
The concept is founded on UniFormat, a hierarchical classification standard arranged by systems and assemblies. This same classification can function as a QA planning tool to develop project team responsibility matrix, decision checklist, and level of development for each project phase. Plus employing UniFormat allows drawings via BIM, specifications including Owner project requirements, and estimates, the three principal factors governing project development to be unified and coordinated from the beginning. When documentation is consistently organized by a recognized standard, the entire team will benefit from the well-coordinated documentation.
To support this approach, Conspectus is developing a new cloud-based tool. This new tool will allow proactive participation by all stakeholders via a transparent process that documents project requirements beginning "day one" and continuously builds the project record in a single location as information becomes available and decisions are made. The information gaps and data loss that occur between design phases each time new documents are created are eliminated. The tool will track the progress, alert missing critical information, collect comments, and record the history as the project progresses. All the while, each stakeholder can watch and actively contribute to the specifications development.
This tool can record Owner project requirements, proposed design solutions by the Design Team, and constructability and budget information from the Construction Team in a single, truly collaborative setting so that essential decisions are not postponed with negative effects on Owner satisfaction, schedule, and construction document production efficiency. Because decisions are documented and dated, all stakeholders can be confident in their reliance on the information.
At the appropriate time, the information is re-sorted into MasterFormat classification for production of contract specifications so project requirements are not lost or forgotten. The tool automatically populates construction specifications with a level of information that makes final editing of specifications easier and less time-consuming.
The increase in complexity of design is not going to decrease. To avoid claims, be profitable, and meet internal aspirations and staff satisfaction, a conscious approach to Quality Management is essential. Firms that do not have adequate QA/QC programs that are consistently implemented are vulnerable to claims and excessive internal production costs. Anecdotally, our experience with construction drawings from design firms of all sizes throughout the country is that the quality of drawings is steadily decreasing and we are concerned that this trend will reach a crisis level.
Each design firm must develop a comprehensive Quality Management program appropriate to its practice. There are many other aspects to Quality Management that are outside the scope of this paper, including business management and evaluation of potential clients. This brief paper is offered in the hope that it may motivate design firms to develop suitable programs for their firms and that suggestions offered herein may help such firms determine what may be missing or under-developed in their Quality Management.
With a conscious effort, the industry can dispell the opinion held by many and clearly expressed by Hal Barcus, one author's architecture professor, "Architecture is never done. You just run out of time, patience, or money." Architecture must be done, and done well with established Quality Management System to fulfill the owner's project requirements.
Owner: The entity contracting for the design and construction of a facility, whether for its own use or as a developer for sale or lease to other end users.
Request for Information (RFI): A written request by the Contractor for clarification or interpretation of contract requirements, or for needed additional information.
Design Team: The architect, interior designers, engineers, and various other consultants who prepare the contract documents for construction. For building construction projects, most Design Teams are led by an architectural firm who fulfills the coordination responsibilities of the building code for what the International Building Code terms the “design professional in responsible charge of the project.”
Quality Management: The organization, implementation, and supervision of quality assurance and quality control processes in a coherent program that is effective to provide the level of quality for deliverables that meets legislative requirements for registrants to protect the public, provides Owner satisfaction, and meets the firm’s goals and aspirations.
Charles Nelson, AIA, FRAIA; Managing Quality in Architecture, Architectural Press; copyright ©2006.
Glenn E. Wiggins, AIA; A Manual of Construction Documentation; Whitney Library of Design; copyright ©1989.
Andrew J. Civitello, Jr; Contractor’s Guide to Change Orders; Prentice-Hall, Inc.; ©1987.
Michael Czap; www.leanarchitecture.com website.